Slide gate plate and nozzle installation

Before installing the upper nozzle on the online ladle, first check the usage of the nozzle block. If there are pits or cracks, use the repair material to repair, and then perform the next step.


Take the upper nozzle brick for trial installation, check the gap between the nozzle brick and the seat brick and the positioning of the nozzle brick. It is forbidden to smash off the upper nozzle head before installing.


Take the upper nozzle brick for trial installation, check the gap between the nozzle brick and the seat brick and the positioning of the nozzle brick. It is forbidden to smash off the upper nozzle head before installing.


When installing the nozzle, the nozzle brick should be smoothly fed into the seat brick, and the mud at the bottom of the nozzle brick should be prevented from falling off and creating gaps during operation.


The water inlet must be replaced when the following conditions exist during installation and use.


The installation and positioning distance of the upper nozzle exceeds the standard range, resulting in the clamping of steel between the upper nozzle and the upper sliding plate or the phenomenon of inability to pull.


The horizontal or vertical aperture of the water inlet exceeds 85mm.